Navigate to "PWA Settings" page from SharePoint online, as shown below.
![]()
Select PWA Settings >> Enterprise Data >> Enterprise Custom Fields and Lookup Tables.
![]()
Then, a list of custom fields displays.
![]()
Our goal is to add some days (Let’s say 21 days) to the existing date custom field.
For this, click on "New Field".
![]()
Give a custom name to the new field and add the days to the existing date custom field in "Custom Attributes" textbox, as shown below.
![]()
Select the "Formula" button and include " [Existing Date field] + add days" and Save.
Let’s Verify
Go to Projects page as shown below.
![]()
Select the project and open "Project Details" page, as shown below.
![]()
From the above screenshot, you can see that "Actual Comm" and "Actual Comm Date" fields are empty. Let us give a date in Actual Comm date.
![]()
Save and close the project.
![]()
Re-open the project and see the result. It displays output as below.
![]()
Thanks for reading my blog. Any suggestions or comments are always welcome.